The problem of installation of concrete batching plant/mixing station exists for a long time, I hope this paper can help customers.
1, Because of the concrete mixing station manufacturing factory with the use of venues generally require long-distance transport, so before installation,it need to check again, to see if the mixer equipment screw loosening, weld rupture, and vent fouling problems.
2, the installation should be carried out step by step, the first mixer host installation, and then the operating console, and then followed by the ingredients, conveyor belt, etc., cement silo can be installed in the final. Step by step to the benefits that the main part of the machine and the minor part can fit tightly and do not cause errors.
3, At the end, installed cable part, this part should be careful, Because of the wrong wiring will cause an accident, but also to ensure the installation of machine components to keep dry, and each groove tube do protection work.
4, after the installation is complete, do not rush to test the machine, and then carefully check again, the test machine to be hours, should be adjusted after each component, and then the whole mixing station test machine.